What is the installation and commissioning process for a graphitization furnace, from equipment arrival at the factory to successful production?May 20, 2026

=IFERROR(@__xludf.DUMMYFUNCTION("GOOGLETRANSLATE(G82, ""zh"", ""en"")"),"

Graphitization Furnace Installation and Commissioning: The Entire Proce"&"ss from Equipment Arrival to Smooth Production

After the graphitization furnace arrives at the factory, the process from installation to commissioning is a systematic project, typically requiring 2-4 weeks. The following is the complete process.<"&"/p>

Phase 1: Preparation (Before Arrival at the Factory)

  • Foundation Acceptance: Check the dimensions, levelness, and bearing capacity of the concrete foundation
  • Supporting Equipment Placement: Pow"&"er distribution, cooling water, gas supply, and exhaust gas treatment systems are ready
  • Tool Preparation: Lifting equipment, installation tools, and testing instruments are in place
  • Personnel Placement: Installation team, electricians,"&" plumbers, and operators are in place

Phase Two: Installation (1-2 weeks)
  • Hoisting and Positioning: Hoisting of furnace body, power cabinet, control cabinet, and vacuum pump unit into place.
  • "&"Mechanical Connection: Piping connection, electrical wiring, and grounding connection.
  • Pipeline Pressure Test: Cooling water pipeline pressure test (1.5 times working pressure).
  • Electrical Testing: Insulation test, grounding test, and phase sequence check.

Phase 3: Commissioning (1-2 weeks)
  • Single-unit commissioning: Independent commissioning of each subsystem (vacuum system, power supply, water co"&"oling)
  • Joint commissioning and testing: Joint operation of all systems to verify interlocks and alarms
  • No-load furnace trial run: Complete one cycle of operation without charging
  • Para"&"meter optimization: Optimize control parameters based on trial run data
    • Phase 4: Acceptance (1 week)
      • Performance Testing: Vacuum degree, temperature field, temperature control accuracy, pressure rise rate
      • Prod"&"uct Verification: Fire a furnace with actual materials to test product performance
      • Training and Handover: Operation training, maintenance training, and document transfer
      • Signing of Acceptance Report
        • Note: During installation and commissioning, the buyer should participate throughout the process and arrange for operation and maintenance personnel to learn on-the-job. This is the best "&"opportunity to familiarize yourself with the equipment; don't miss it.

")