I. Standard Payment Milestones and Ratios
The standard payment process we recommend is as follows, with specific ratios negotiable based on project scale:
-
After Contract Signing:Pay50%of the total contract price as an advance payment.
-
Purpose: Used for project initiation, procurement of core raw materials and components such as steel, stainless steel plates, and major purchased parts (e.g., vacuum pumps, power supplies, PLC).
-
-
After Factory Acceptance Testing (FAT) and Before Shipment:Pay30%of the total contract price as a shipment payment.
-
Purpose: Covers the main costs of equipment manufacturing and arranges shipment.
-
-
After On-Site Installation, Commissioning, and Site Acceptance Testing (SAT):Pay10%of the total contract price as a commissioning payment.
-
Purpose: Settles the final payment for installation and commissioning.
-
-
After the One-Year Warranty Period Expires:Pay10%of the total contract price as a warranty retention.
-
Purpose: Serves as a guarantee for our performance of warranty period services.
-
-
II. Rationale of the Payment Method
This ensures we have the necessary funds to initiate the project in the early stages of manufacturing, while also giving you sufficient at key milestones such as equipment shipment, installation, commissioning, and stable operation. It embodies the principle of shared risks and win-win cooperation.